Safe isolation, draining, and removal of a gravity hydraulic davit system, with full attention to personnel safety and the environment.
Safe, controlled dismantling of a gravity hydraulic davit system on an offshore rig in Abu Dhabi, with the focus on personnel safety, environmental protection, and proper worksite management.
A comprehensive marine and offshore engagement for Crystal Offshore Middle East, delivered on the HEA KRAKEN Rig at KIZAD Port, Abu Dhabi. Over three days, from 16 to 18 July 2024, the project focused on protecting personnel, safeguarding the environment, and keeping the worksite well organized, so that rig operations ran safely, responsibly, and efficiently from start to finish.


Scope of Work
The work followed a clear sequence, from isolating the hydraulic system to inspecting the finished work area, with personnel safety and environmental protection built into every stage.
Dismantling was carried out over three days (16-18 July 2024), with the hydraulic system safely isolated, its fluid collected for proper disposal, and the work area inspected and cleared in line with environmental requirements.
Project Overview
We handled the job from first isolation to final inspection, keeping personnel safety and environmental protection at the centre of every step.

Let's Connect
From technical requirements to complete flow control solutions, our team is ready to understand your needs and help you move forward with confidence.